Schedule

 

Milestone Time
Mission Requirements Review
 
End of April 2005
System Requirements Review
  
Mid-June 2005
Preliminary Design Review
followed by purchasing processes, detailed satellite design and production of engineering models of the satellite subsystems
 
November 2005
Bench tests of engineering models in SSC's laboratories
 
September 2006
Vibration tests of the two structural test models
December 2006

Guidance, navigation and control system simulations started in SSC's satellite laboratory
 

October 2006
Critical Design Review
 
January 2007
Delivery of flight hardware and experiments
 
June-December 2007
AIT (Assembly, Integration and Test) of the vehicles and their subsystems started
 
September 2007-April 2008
Advanced system tests of the satellites
 
May-October 2008
Environmental tests (vibration, thermal cycling, EMC etc)
 
October 2008-February 2009
Flight acceptance review
at which it is decided if the satellites are ready for launch
 
May 2009
Spacecraft ready for transportation to launch site
 
November 2009 
Launch from Yasny (Russia) April 2010, but is delayed due to a delayed contract between Russia and Kazakhstan

AIT took place in the clean room facilities at SSC's engineering center in Solna. Environmental tests at system level were performed at Packforsk near SSC's premises and at Intespace in Toulouse, France.